SISECAM SODA LUKAVAC ESP PROJECT FOR BOILERS NUMBER 6 AND 7

POLITEKNIK ENGINEERING SERVICES & MANUFACTURING LTD., signed a contract for the improvement of electrostatic precipitators of the power plant at Sisecam Industrial Soda Factory seated in Bosnia-Herzegovina in 2013.
 
The contract relates to improvement of the chambers of two electrostatic precipitators for three consecutive years.
 
Improvement works planned for the first stage were performed in July 2013, and part of the plant was successfully commissioned.
 
Improvement works planned for the second stage were performed in July 2014, as a result of which one of the electrostatic precipitators available at the plant was completely improved and subsequently commissioned. The dust emission value obtained therein is below 40 mg/Nm3.